Capella Laboratory, Cambridge, UK

  • Type de bâtiment:
  • Education & Culture
Plein écran Fermer

A new laboratory for Cambridge University based on the Addenbrooks Hospital site.

Featuring 489nr DELTABEAM® @ 2.75km, the design required very low response factors due to sensitive lab equipment.

The origional cast in-situ design was for a 700mm deep slab but after a lot of work it was shown that D32-500 DELTABEAM® Composite Beams along with 300mm deep hollowcore with a 200mm structural topping would meet the vibration performance specfication.

DELTABEAM® along with other offsite methods allowed the construction time to be 20 weeks faster and reduced over 500 truck deliveries when compared to the cast in-situ solution.  

Lire la suite down-arrow.png

Our onsite construction program was 20 weeks faster and saved over 2,500 man weeks in comparison with the envisaged in-situ solution. Additionally the overall carbon footprint was significantly reduced with fewer truck deliveries and high quality offsite production of the steel Deltabeams and precast concrete units

Nickie Brown, Managing Director PCE Ltd

Détails du Projet

Taille du projet:
17,000 m2
Étages:
7
Entreprise de construction:
PCE Ltd
Designer structurel:
ARUP
Architect:
Fairhurst Design Group
Année de réalisation:
2016
Année de livraison:
2017

Parlez avec nos experts

Michael Scott

Michael Scott

Sales Manager, Deltabeam Products

England & Wales

Tel. +44 1325 318619
Mob. +44 755 7118470
[email protected]